WINTER UPDATE: Renovations Continue, Permits in the Works
It may be getting cold outside, but work continues at both sites into the winter months:
Bird Island Renovations:
Work is almost done on the gym's athletic flooring—it's 98% complete! The pintle and volleyball sleeves should be installed by the week ending December 20 and the bleacher installation is almost done. Work installing the stage curtains is also 85% complete.
Olivia Renovations:
The pool exterior restoration is coming along nicely, almost 90% complete, and demolition of the interior walls has begun. Additionally, storm shelter fencing, removals, and utility relocation are underway, with footing excavation and pouring expected to begin after the new year.
Progress on permits is moving along as the state review and comment has been addressed and resubmitted as of December 9. Next phases of work are scheduled to begin in June 2025, but there ispotential some might get started a bit earlier so stay tuned!